Grand Avenue Cycleway and Improvement Scheme

Client: Brighton & Hove City Council

Value: £ 1.4 million

This wide victorian street was a perfect location to install a one mile cycleway stretching almost the length of Hove from the coast and back. Historically a dual carriageway, one lane was removed on each side to make room for a 1.5 metre traffic-free cycleway on either side of the carriageway.

Planning, Design & Consultation:

RJ Dance Contractors LimitedWith the help of a CDM co-ordinator and designer issues that had to be mitigated were; working on top of basements, provisioning access/egress and maintaining traffic flow at all times. Key stakeholders including engineers, residents’ associations, schools, emergency services, and working groups were consulted in the weeks prior to the works.

These groups identified a series of issues which would need to be mitigated before commencement of the works such as health & safety of school children and residents, how best to manage the traffic during the works, how best to locate services and any contingent plans for hospitals etc, what were the lines of communication open to the stakeholders, what design was most practical and what materials were best suited to this location.

The feedback received from stakeholders was included in the final designs and plans which were approved by the local authority shortly before works commenced.

Build & Implement:

Before works commenced, our health & safety manager, the CDM coordinator, the project manager, and the engineer met onsite to discuss the programme of works. Once the programme was agreed each stakeholder signed off the project with a view to meeting regularly throughout the works. The works commenced on schedule. Where possible, we used our own resources and limited the use of subcontractors.

The total project took 6 months to complete. If variation orders were issued these were fed back to the programme director and quantity surveyor for a possible reallocation of resources. With the help of our CDM coordinator, we located the services of statutory undertakers. Where necessary, we made provision for their adjustment / repair or simply noted them for future reference.

As the project progressed, changes to the plans were noted and recorded in the final plans held with the local authority.

Project Completion, Maintenance and Benefits:

grand-avenue-2001-299x190Residents of Brighton & Hove now have access to an off-street cycle highway stretching from the coast to the centre of Brighton and beyond. Families can now cycle on a traffic free cycle network through Brighton & Hove. There are plans to extend this in the future. R J Dance have been chosen as a main contractor again.

The works were completed within the time scale alloted. Before we left site, we met with the various stakeholders associated with the project to resolve any issues and ask for signoff. Feedback to our projects is always welcome – that is one of the ways that helps to improve our service.

The feedback so far has been positive. The local authority will closely monitor progress over the coming months to ensure that the improvements continue to offer the benefits required.